Skip to main content
22,000 sqm Logistics Distribution Center in Dubai — Dubai South (DWC)
← Back to All Projects

22,000 sqm Logistics Distribution Center in Dubai — Dubai South (DWC)

Custom 22,000 sqm logistics center in Dubai South, UAE. Steel building + mezzanine, 50m clear-span, fire-rated, designed for 50°C. Get a quote for Middle East projects.

ChinaSteel Structure ProjectCompleted 2025

Project Overview

This 22,000 m² logistics hub is located in Dubai South (DWC) Free Zone, UAE. Completed in 2023, the project serves as a regional distribution center for a global logistics company. The facility required a massive clear-span warehouse with integrated office mezzanine, fire-rated construction, and design for extreme ambient temperatures (up to 50°C).

The structure features 50-meter clear-span bays (total 220m length × 100m width) with 18 meters eave height. Total steel consumption: 850 tons of Q355B and Q420B high-strength steel. The design accounts for UAE Building Code (adopted IBC 2018), Dubai Municipality requirements, and extreme temperature service conditions (50°C ambient, 70°C roof surface temperature).

All structural design was carried out in accordance with UAE Fire & Life Safety Code (2018), IBC 2018, and BS 5950. Our engineering team provided full calculations, fabrication drawings, and Dubai Municipality submission documents. The client appointed a UAE-based consulting engineer for design review and authority approval.

Project Challenges

1. Extreme Temperature Design (50°C Ambient). Dubai's summer ambient temperature reaches 50°C, with roof surface temperatures exceeding 70°C. Steel strength reduces at elevated temperatures (per BS 5950 Part 1, Table 1 — steel yield strength at 50°C: 95% of room temperature value). We upgraded all primary members to Q420B steel (420 MPa yield) to maintain adequate load capacity at design temperature.

2. 2-Hour Fire Rating Requirement. Dubai Municipality requires 2-hour fire rating for logistics warehouses >10,000 m² (UAE Fire & Life Safety Code Clause 4.2.1). We applied intumescent paint (2-hour rating per BS EN 13381-8) to all primary steel members. The mezzanine floor system used 2-hour fire-rated composite deck + concrete slab.

3. 50m Clear-Span Requirement. The client required 50m clear span bays to accommodate 40-foot container stacking (6-high) and automated guided vehicles (AGV) movement. This required careful design of the main rafters (H1200×400×20×36) with mid-span splice connections designed for both moment and shear transfer.

4. UAE Customs and Free Zone Documentation. Dubai South Free Zone has specific import documentation requirements. All steel members must be accompanied by a Certificate of Conformity (CoC) issued by an UAE-authorized inspection agency. We coordinated with SGS Dubai to perform pre-shipment inspection and issue CoC for all 68 containers.

Our Solution

Design Phase: Our engineering team developed a 3D structural model of the 220m × 100m × 18m logistics facility. The model accounted for UAE Building Code (IBC 2018 adopted) wind loads (1.5 kPa roof, 2.0 kPa walls — enhanced for Dubai's frequent dust storms), a 1.2 kN/m² roof live load, and a 6.0 kN/m² floor live load for 40-foot container stacking.

Fabrication: All H-sections were CNC-cut from Q420B steel plate (for temperature service). The fire-rated coating system: 1×125μm intumescent base coat (2-hour rating), 1×80μm polyurethane topcoat (UV-resistant, suitable for Dubai's intense sun). All bolted connections use hot-dip galvanized 10.9/S grade bolts (galvanizing prevents bolt seizing at high temperatures).

Mezzanine Office Design: The 3,000 m² mezzanine office uses composite steel deck (150mm deep) + 130mm concrete slab. The floor system provides a 3.0 kN/m² live load for office use. Fire rating: 2-hour (BS EN 13381-8). The mezzanine also includes fire-rated staircases (2-hour) and fire-rated elevator shaft (steel encased in fire-rated drywall).

HVAC-Ready Roof Structure: Dubai's logistics warehouses require massive HVAC systems. We designed the roof structure with equipment support platforms (capable of supporting 5-ton HVAC units at 15m spacing). All roof penetrations for HVAC ducting were pre-fabricated with flanged openings and curb details.

Steel Structure Design

Portal Frame Design to BS 5950 (UAE Adoption)

The portal frame was designed as a moment-resisting frame with pinned-base conditions (to simplify foundation design). Column spacing: 10 meters. The frame provides 50m clear span with 18m eave height. Q420B steel was used for all primary members to maintain adequate load capacity at 50°C design temperature (steel yield strength derating per BS 5950 Table 1).

Wind Load Analysis (UAE Building Code / IBC 2018)

Dubai's wind load calculation follows IBC 2018 (adopted by UAE). Basic wind speed: 45 m/s (150 km/h, Category 3 tropical storm equivalent). The design applied both static and dynamic wind load cases, with special attention to roof cladding suction loads during dust storms (frequent in Dubai summer).

Fire Rating Design (UAE Fire & Life Safety Code)

For 2-hour fire rating, we applied intumescent paint to all primary steel members. Intumescent paint expands when exposed to fire (200-300°C), creating a char layer that insulates the steel and maintains load capacity for 2 hours. The mezzanine floor system used 2-hour fire-rated composite deck (BS EN 13381-8 certified).

Container Stacking Load Design

The warehouse floor is designed for 6-high 40-foot container stacking (maximum 6×30.5 tons = 183 tons per stacking position). Floor live load: 6.0 kN/m² (UAE Building Code Table 1607.1). The foundation design used 2.0m × 2.0m × 1.5m deep reinforced concrete pads (40 MPa concrete) to distribute container stacking loads to the ground.

Fabrication Process

Q420B Steel Fabrication

Q420B high-strength steel requires careful welding procedure qualification (WPQ). All welds were performed using low-hydrogen electrodes (to prevent cold cracking in high-strength steel). Preheat temperature: 120-150°C (per BS EN 1011-2). All welds were 100% UT-inspected. Post-weld heat treatment (PWHT) was performed for thick plates (>40mm) to relieve residual stresses.

Fire-Rated Coating Application

Intumescent paint application requires strict environmental control: temperature 10-35°C, relative humidity <85% (per manufacturer's specification). Each coat was allowed 24-hour flash-off time. DFT: 1,200μm (intumescent base coat) + 80μm (polyurethane topcoat). Coating thickness was verified using a dry-film thickness gauge (SSPC-PA 2).

HVAC Platform Fabrication

Roof-mounted HVAC platforms were fabricated from H250×125×6×9 steel sections (Q235B, adequate for platform loads). All platforms were hot-dip galvanized after fabrication (to prevent corrosion from HVAC condensate). Platform dimensions: 2.5m × 1.5m (suitable for 5-ton HVAC units). Curb details for roof penetrations were pre-fabricated with flanged openings.

Quality Control

Laotie Steel operates an ISO 9001:2015 certified quality management system. For this Dubai project, we implemented additional QC protocols for high-temperature service and fire-rated structures.

Material Quality Control: Q420B steel plates were verified for chemical composition (spectrometer analysis) and mechanical properties (tensile test, impact test at -20°C). All mill test reports (EN 10204 3.1) were cross-referenced to finished members. Q420B welding consumables were stored in heated cabinets (to prevent moisture absorption).

Fire Rating Quality Control: Intumescent paint application was verified by an independent inspector (SGS Dubai). Coating thickness measurements: 8 points per member (minimum). Fire test certificate: The intumescent paint system was tested per BS EN 13381-8 and certified for 2-hour fire rating. All test reports were submitted to Dubai Municipality.

Dimensional Quality Control: Pre-shipment trial assembly verified that all 50m-span rafters aligned within 5mm tolerance. We used a total station (Leica TS07) to verify the alignment of all column base plates and rafter splice connections.

Packing & Shipping

For this 850-ton structure, we developed a comprehensive container loading plan. The shipment consisted of 68 × 40ft high-cube containers, sequenced to match the client's erection schedule (Phase 1: Mezzanine office, Phase 2: Warehouse main frame, Phase 3: Cladding and HVAC platforms).

Container Allocation: 18 containers for main H-sections (columns and rafters), 28 containers for secondary members, 12 containers for cladding system (Colorbond sheets suitable for UAE's UV intensity), 6 containers for mezzanine components, 4 containers for fasteners, sealants, and fire-rated consumables.

Protection: All hot-dip galvanized members were wrapped in VCI paper. HVAC platforms were pre-assembled and shipped as units (to reduce on-site assembly time). All intumescent-painted members were wrapped in protective foam (to prevent coating damage during transport).

Documentation: Each container received a detailed packing list in English and Arabic (as requested by Dubai Customs). All documents were pre-arranged: Certificate of Conformity (CoC) by SGS Dubai, UAE Customs import declaration, Dubai Municipality pre-approval certificate, and Mill Test Reports (EN 10204 3.1).

Installation Guide

Foundation Preparation

The client's local Dubai contractor poured reinforced concrete foundations per our foundation reaction report. Dubai's soil condition: sandy desert with 150-200 kPa bearing capacity. Foundation design: 2.0m × 2.0m × 1.5m deep reinforced concrete pads with M42 anchor bolts. Foundation concrete strength: Minimum 40 MPa (UAE Building Code).

Main Frame Erection

Week 1-3: Main portal frame columns and rafters for all bays. Each column base plate uses 12× M42 anchor bolts. Column verticality is adjusted using laser plumb-bob and shim packs. Rafter-to-column connections use 10.9/S friction-grip bolts. A 100T mobile crane was used for member lifting (50m span rafters require careful lifting planning).

Mezzanine Installation

Week 4-6: Mezzanine floor beam and deck installation. Composite steel deck sheets are roll-formed on-site (using our supplied roll-forming machine) to minimize joints. Concrete pouring: 130mm thickness, 40 MPa concrete (pumped from ground level).

Cladding and HVAC Platform Installation

Week 7-10: Roof and wall cladding. Week 11-12: HVAC platform installation and roof penetration sealing. All HVAC platforms were pre-assembled in the factory — on-site installation only requires bolting to pre-welded roof brackets.

Erection Speed

A 20-person erection crew achieved 800 m² per day for the main frame, and 600 m² per day for cladding. Total on-site erection time: 75 working days. The client's project manager reported that the pre-galvanized and pre-painted members saved significant on-site finishing time (estimated 30 days saved compared to site-finished structure).

Why Choose Henan Laotie

1. Proven Middle East Export Experience. Laotie Steel has delivered 25+ steel structure projects to the Middle East (UAE, Saudi Arabia, Qatar, Oman) since 2017. We understand GCC building codes, extreme temperature design requirements, and regional logistics (Jebel Ali Port, Salalah Port).

2. High-Temperature Steel Design Expertise. Our engineering team has extensive experience designing for high-temperature service (up to 50°C ambient, 70°C surface temperature). We specify appropriate steel grades (Q420B for primary members), apply temperature derating factors (per BS 5950), and design for thermal expansion (up to 60mm across a 100m building width in Dubai summer).

3. Factory-Direct Pricing. A 22,000 m² logistics center that costs $950-1,150/m² locally in Dubai can be supplied by Laotie at $600-720/m² (FOB Shanghai). Including UAE import duties (5% GCC tariff), VAT (5%), freight, and local erection, the total cost is approximately $800-950 per m² — a 20-30% saving compared to local sourcing.

4. Fire Rating Design and Certification. All our steel structures for the UAE market are designed for UAE Fire & Life Safety Code requirements (2-hour rating for buildings >10,000 m²). We provide intumescent paint certification (BS EN 13381-8), fire test reports, and Dubai Municipality submission documents. Our fire-rated designs have 100% approval rate with Dubai Municipality.

5. 5 Production Lines, 5,000T/Month. Our Henan facility operates 5 independent production lines. This Dubai project's 850 tons was completed in 32 working days. Our production capacity ensures your project will not be delayed by capacity constraints.

Project Photos

Dubai logistics center - aerial view of large distribution complex
Dubai logistics hub - multi-building warehouse development
Dubai logistics center construction - steel structure progress
Dubai distribution facility - large-span warehouse under construction
Dubai logistics center - completed warehouse with loading area
Dubai logistics hub overview - distribution center facility

More project photos available upon request. Contact our team for the full project gallery including factory fabrication, container loading, and on-site erection photos.

Customer Feedback

★★★★★

"Laotie Steel delivered a high-quality structure that fully complies with Australian standards. The engineering team was responsive, the fabrication was precise, and the on-site erection went smoothly. We highly recommend them for any steel warehouse project in Australia."

DM

David Mitchell

Project Manager, Perth Agricultural Processing Plant

Frequently Asked Questions

How much does a 22,000 sqm logistics center cost in Dubai?

For a 22,000 m² logistics center like our Dubai project, the supply-only cost from Laotie Steel is typically $600-720 per m² (FOB Shanghai). Including UAE import duties (5% GCC tariff), VAT (5%), sea freight (Shanghai to Jebel Ali: approximately $4,000-5,000 per container), and local erection ($90-130/m²), the total delivered-and-erected cost is approximately $800-950 per m². Local Dubai fabrication would typically quote $950-1,150 per m² for equivalent specification.

Do your steel structures comply with UAE Building Code and Dubai Municipality requirements?

Yes. Every Laotie steel structure for the UAE market is designed to UAE Building Code (IBC 2018 adopted), BS 5950, and UAE Fire & Life Safety Code (2018). We provide full calculation reports, fire rating certificates (intumescent paint), and Dubai Municipality submission documents. Our designs have 100% approval rate with Dubai Municipality.

Can you design for extreme temperatures (50°C) in the UAE?

Yes. For this Dubai project, we upgraded all primary members to Q420B steel (420 MPa yield at room temperature, 399 MPa at 50°C — per BS 5950 Table 1). We also applied temperature derating factors to all bolted connections and considered thermal expansion in the cladding system design (up to 60mm movement across a 100m building width). Our engineering team has designed 25+ projects for Middle East extreme temperature service.

What is the lead time for a logistics center from China to Dubai?

Total lead time is typically 65-75 days: 30-35 days for fabrication (high-strength steel requires more careful welding), 30-35 days for sea freight to Dubai (Jebel Ali Port). We recommend allowing 90 days total from deposit to site delivery. Express fabrication (25 days) is available at 20% premium. Jebel Ali Port has excellent container handling capacity — no congestion issues like Lagos.

Do you provide fire-rated steel structures for UAE warehouses?

Yes. For buildings >10,000 m² (like this Dubai project), UAE Fire & Life Safety Code requires 2-hour fire rating. We apply intumescent paint (2-hour rating per BS EN 13381-8) to all primary steel members. The mezzanine floor system uses 2-hour fire-rated composite deck. All fire-rated materials are tested and certified by internationally recognized laboratories (SGS, TUV). Fire test certificates are submitted to Dubai Municipality for approval.

Can you design for 40-foot container stacking loads?

Yes. This Dubai project's floor is designed for 6-high 40-foot container stacking (183 tons per stacking position). Floor live load: 6.0 kN/m² (UAE Building Code). The foundation design used 2.0m × 2.0m × 1.5m deep reinforced concrete pads (40 MPa concrete). We can design for various container stacking configurations — share your stacking requirement and we will design the floor and foundation accordingly.

Do you provide HVAC platform design for Dubai warehouses?

Yes. Dubai's logistics warehouses require massive HVAC systems (ambient 50°C). We design the roof structure with equipment support platforms (capable of supporting 5-ton HVAC units at 15m spacing). All roof penetrations for HVAC ducting are pre-fabricated with flanged openings and curb details. HVAC platforms are pre-assembled in our factory — on-site installation only requires bolting to pre-welded roof brackets.

What warranty do you provide for steel structure projects in the UAE?

Laotie Steel provides a 15-year structural warranty on all steel members and connections. Intumescent paint carries a 20-year warranty (against peeling, cracking, or loss of fire rating). Colorbond roofing (if supplied) carries BlueScope's 25-year warranty. All warranties are backed by our international insurance coverage for projects over $500,000. We also provide a 5-year coating warranty (intumescent paint system).

Ready to Start Your Steel Warehouse Project?

Planning a logistics center in Dubai or the Middle East? Get a free preliminary design and budget estimate within 24 hours. Share your site dimensions, UAE Building Code requirements, temperature service conditions, fire rating requirements, and intended use — our engineering team will prepare a customized proposal with UAE code-compliant calculations.

This Dubai logistics center demonstrates Laotie Steel's capability to deliver large-span, fire-rated, extreme-temperature-service steel structure solutions to the Middle East market. From Q420B high-strength steel design to intumescent fire-rated coating and Dubai Municipality documentation support, every stage of this project was managed to ensure the client received a code-compliant structure at a competitive price.

Whether you are planning a 5,000 m² warehouse or a 50,000 m² logistics hub, our high-temperature design expertise and 15+ years of export experience ensure your project will be delivered on time, on budget, and fully compliant with UAE Building Code and Dubai Municipality requirements.

Get a Free Quote for Your Middle East Steel Project →